Time

(week beginning)

Task

Staff responsible

 

17th February

 

Investigation to be finalised

Equipment to be purchased.

Staff honoraria to be decided.

Time off timetable to plan investigation to be arranged.

ICT rooms to be booked

 

JC, MR

JC

JC

JC, MR, LH

 

MR

Half-term holiday

 

 

 

3rd March

 

Cross-curricular links with Science to be checked

Sites to be decided

Fieldwork tasks to be tested

 

 

JC

MR, JC

MR, JC

 

10th March

 

ICT activity to be decided

 

All in dept meeting

 

17th March

 

Fieldwork booklet to be written

 

JC, MR

 

24th March

 

Investigation write-up instructions and assessment guidelines to be produced.

 

JC, MR

 

31st March

 

Timetable for classes to be organised.

Digital cameras to be booked/liaise with ICT staff

 

MR

 

MR

 

7th April

 

Final arrangements presented in departmental meeting.

Fieldwork booklets and assessment writing guidelines in for photocopying.

 

MR

 

MR

Easter holiday

 

 

 

28th April

 

 

Ecosystems module begins:

Lessons on ecosystem basics.

 

All

 

6th May (Tues)

 

 

Lessons on characteristics of deciduous woodlands.

Fieldwork begins.

 

All

 

12th May

 

 

Fieldwork.

Investigation write-up and ICT.

 

All

 

19th May

 

 

Investigation write-up and ICT.

Initial evaluation of project in departmental meeting.

 

All

 

All

Half-term

 

 

 

2nd June

 

Project to be fully evaluated in departmental meeting.

 

All, led by MR